We are excited to share with you that the LRBT RYK hospital and residences structure is now complete with finishing work being carried out at different stages.
The construction started on 25th June 2022 and is scheduled to be complete in June 2024. Despite many administrative hurdles such as unavailability of utilities and clearances from District Authorities, the project is progressing and it’s 65% complete.
This project is being funded by a UAE-based donor and covers land, construction and equipment of this hospital. This donor has in the
past funded major renovation and expansion at our Khanewal and Gambat hospitals. This was followed by construction of a new OPD
and surgical complex at Lar, and a new hospital building at Mandra which was completed last year.